To submit a report by the Maritime and Country Parks Officer.
Minutes:
The Senior Manager – Economy and Community referred to the Dredging
Strategy and noted that Alan Williams (Coastal Engineering UK Ltd) had been
commissioned together with Gwynedd Consultancy to look at the options in terms
of strengthening the Crib Groyne and reducing the
sediment.
A presentation was given by Alun Williams providing details about his
work in assessing and reviewing the Crib Groyne. He
drew attention to four possible options and an estimate of the cost involved,
namely:
1. Minimum maintenance of the existing structure (£10-15,000);
2. Higher level maintenance and reinstatement of the existing structure
(£35-40,000);
3. Vertical extension/encasement of the existing structure using a combination
of (a) crib steelwork or (b) sheet piling and rock armour (£125-135,000 (a) or
£225-240,000 (b)); or
4. Encasement of the existing structure in rock armour (£140-150,000).
The following considerations were highlighted in terms of the options:
·
Both options 1 and 2
require minimal intervention and will provide some but little in the way of
improved performance compared to existing conditions;
·
Options 3 and 4 by
virtue of both increased elevation and improved robustness and integrity will
reduce both transmission through and movement over the structure; however
·
Over a ten year period,
the present value of costs of these options was likely to be higher than
continued practice of dredging and removal; and
·
Options 1, 2 and 4 were
the most flexible in terms of adaptability in future arrangements.
Members were given an opportunity to provide observations and ask
questions to the consultant, and he responded to them as follows:
·
In regards to increasing
the length of the Crib Groyne, increasing the length
of the Crib Groyne had not been included in his brief
and more detailed work in term of modelling, assessing the impact and
environmental considerations would need to be done. He noted that work needed
to be done in the short term;
·
Could possibly consider
moving the trailing arm more to the left when assessing long term options;
·
That using heavy rock
armour or pre-fab concrete structures to reinforce, rather than a steel
structure and moving the trailing arm so that it can enter deep water, was
something to consider.
·
Agreed that option 3
would only prevent the situation from deteriorating for a period, but was
presented as not to rule it out as a possible option;
·
Annual maintenance was a
financial burden and therefore a study of the long term options was needed in
regards of the Crib Groyne and to also consider
moving the direction of the other arm.
The Senior Manager Economy and Community noted that the service was
eager to implement a short term solution in the coming months. He added that a
long term solution would be a 2-3 year process, therefore, it was necessary to
implement a short term solution that would not restrict the possible long term
options.
The Pwllheli Marina Berth Holders' Association
Representative noted that it should be considered to increase the length of the
Crib Groyne gradually in order to see to what length
it could be extended to without complicating the process to assess if it was
effective.
The Chair noted that something needed to be done in the short term
before considering the long term options.
It was suggested to ask Gwynedd Council to progress with Option 4 to
strengthen the current structure by encasing the structure with a rock armour.
The proposal was seconded.
RESOLVED to ask Gwynedd
Council to progress with Option 4 which is to strengthen the current structure
by encasing it in rock armour.
The Senior Economy and Community Manager noted that a copy of the report
would be circulated to the members in order for them to provide observations
within three weeks. He confirmed that the service would progress in accordance
with the wishes of the Committee.
The Chair thanked the consultant for his presentation.
The Maritime and Country Parks Officer guided the members through the
report, drawing attention to the following main points:
·
That the Members Support
Officer had corresponded with every harbour organisation representative to
remind them of the need to nominate a representative for the coming year and to
also send a copy of the constitution and minutes of the annual meeting of the
relevant groups. It was noted that the necessary information had been received
from the Pwllheli Marina Berth Holders' Association, Pwllheli Town Council and the RNLI. Those who were yet to
respond were asked to send the information to the Members Support Officer in
the coming weeks.
·
That there were 60 boats
on annual moorings in the outer Harbour in 2017 compared with 58 in 2016.
·
It was confirmed that
306 boats were on annual pontoon moorings in the Hafan
in 2017, compared with 287, which were on pontoon moorings in 2016. The
increase was encouraging and it was assumed that the change to charge fees on a
Length Overall (LOA) arrangement had helped, and it was hoped that there would
be an increase in numbers from year to year.
·
That the Government's
Department for Transport had published modifications to the Ports' Safety Code
in November 2016. Copies of the new code had been circulated to all Members of
the Consultative Committee and copies could also be obtained on the MCA's
website.
·
Between 19 and 21
September 2017, a thorough inspection was carried out by the Coastguard
Agency's auditors on the current safety arrangements and systems of Gwynedd
municipal harbours in order to ensure compliance with the Ports' Safety Code.
The initial opinion of the auditors was that the Council complied with the
requirements in general but that some aspects relating to recording duties and
identifying the Duty Holder needed to be amended. The inspectors visited the
harbours of Aberdyfi, Porthmadog
and Pwllheli during the inspection. In terms of Pwllheli, an observation was made by the auditor that the
Channel was narrow when the tide was out.
·
The draft written report
was awaited in the following week. It was explained that the Council had a
specific period to revise its arrangements and the Coastguard Agency would
revisit the service within 12 months of submitting the report when
recommendations submitted in the report would be expected to be actioned. It
was noted that copies of the final report would be circulated to members.
·
Following a discussion
with the auditors, it had been agreed in principle that it would be beneficial
for the date of the second visit to coincide with the date of a Harbour
Consultative Committee. It was suggested to the auditors that it could be
beneficial for the auditors to attend a meeting of the Porthmadog
Harbour Consultative Committee and to invite representatives from the
Consultative Committees of Aberdyfi, Barmouth and Pwllheli to the
meeting in October 2018.
·
A detailed inspection
had been conducted by Trinity House Lighthouse Authority inspectors on 2 August
2017, and no matters had arisen.
·
Thus far, three reports had
been submitted to the attention of the Marine Accident Investigation Branch
(MAIB) reporting on events relating to boats in Gwynedd. One event reported on
was a boat which capsized within an authorised area of Pwllheli
Harbour. A power boat was travelling from the direction of Abersoch
to Pwllheli at a safe and reasonable speed when the
boat was capsized by a wave. The sailors suffered no injuries and the boat was
retrieved by the Lifeboat crew.
·
That the service was
considering improvements to the equipment and fuel service. The possibility for
customers to receive and pay for fuel through self-service machines was being
investigated. If it would be possible to introduce the service, customers would
then be able to obtain fuel by using the self-service equipment outside the
hours of 09.00 - 17.00. Before it could be possible to confirm the self-service
arrangements, the Service needed to consider how they would be able to ensure
that users complied with the requirements of submitting red diesel statements.
This was related to processing and collecting additional toll payments in
regards to selling red diesel used by boats for the purpose of travelling by
boat. It was hoped that there would be no administrative barriers to improving
customer service.
·
The work of dredging the harbour entrance
had been completed during the spring and following the dredging work, further
work had been completed to level the surface of the channel to try to ensure
consistency in the navigation channel bed levels.
·
In order to meet with
the budget challenge and the service's income target, it was suggested to
increase Hafan and Pwllheli
harbour fees by 2% on average for the 2018/19 financial year. It was emphasised
that only a draft had been submitted in the agenda, and that the fees were
subject to receiving confirmation from the Cabinet Member - Economic
Development, and that they would be confirmed at the next meeting.
The Maritime and Country Parks Officer emphasised the importance of
ensuring that every power boat and Personal Watercraft which used the Hafan's slipway was registered and that it displayed the
registration permit on the boat. No boat should be launched in the harbour
without displaying the registration permit. It should be ensured that Park and
Launch companies complied with these requirements.
The Pwllheli Marina Berth Holders' Association
representative noted that some individuals used the slipways early in the
morning and returned late in the evening to avoid paying and registering. He added that moving the Harbourmaster's office had had an impact
and that businesses could not be there at all times.
In response to a question
by a member, the Maritime and Country Parks Officer noted that
the CCTV facilities had been
improved. It was impractical
for officers to watch hours of video footage, therefore individuals were asked to contact
the service as soon as possible following a specific incident.
A member noted that individuals also launched boats where they were not
permitted to do so. In response, the Maritime and Country Parks Officer noted
that there was a new boat in the harbour that would be of assistance to
carry-out more patrolling work. He added that were more staffing resources with
the addition of the Hafan staff, and staff's job
descriptions were currently being reviewed, and it was anticipated that the
situation would improve in 2018.
In response to a comment by the Pwllheli and
District Boat Owners Association Representative, the Maritime and Country Parks
Officer noted that the service would provide him with ropes and a fender and
that he should contact the Harbour Manager to arrange this.
The Pwllheli Sailing Club and Plas Heli representative noted
that there was a need to look at dredging within the Hafan.
In response, the Maritime and Country Parks Officer noted that a hydrography
survey had been conducted on the basin, and that there was an intention to
assess the survey before deciding on which steps to take. He added that emptying the stilling lagoon was
being considered. In response to an observation by the RNLI representative in
regards to locally disposing of the material, the Maritime and Country Parks
Officer noted that no location in the bay had the appropriate licence.
The Maritime and Country Parks Officer referred to extreme weather during
the previous night as a result of former storm Ophelia. The Pwllheli
Harbour Manager noted that considering the extreme weather, the only damage was
that one sail had blown out.
The Pwllheli Marina Berth Holders
Association Representative noted that the Maritime and County
Parks staff had worked hard during that
day/night and asked that
the gratitude of the boat owners be conveyed to the staff.
He added that no significant complaints had been submitted by members of the association this year.
A copy of the Harbour and Hafan's final budget
summary for 2016-17 and an update on the 2017-18 budget up to the end of
September 2017 was shared in the meeting. Their content was expanded upon and
it was noted that the financial situation was better in the current year and it
was hoped that the targets would be reached.
The Maritime and Country Parks Officer referred to the Glandon beach car park and noted that the surface of the
car park would be addressed before the end of October. The potholes that had
appeared on the car park's surface by the entrance were filled at the beginning
of the season. He explained that due to
the busyness of the site and number of vehicles which used the car park, the
service would be considering alternative arrangements to try to reduce the
damage caused to the surface of the site.
The representative for Pwllheli Town Council
noted that the condition of the car park needed to be addressed as the potholes
on the surface were dangerous for older people.
The Pwllheli Sailing Club and Plas Heli representative noted
that matter was discussed daily by staff at Plas Heli and that it made them feel disheartened.
In response to the comments, the Maritime and Country Parks Officer
noted that a long term solution would be sought for the situation.
An update was received by the Pwllheli Sailing
Club and Plas Heli
representative about events in Plas Heli. He noted that one World championship and one British
competition had been held during 2017. He added that an Optimus competition would
be held in 2018 and preparations for a competition in 2021 were
progressing.
RESOLVED to note and accept the report.
Supporting documents: