To delegate powers to the Assistant Head of Department to
approve the application, subject to the following conditions:
• Commence
the development within five years
• 14 days'
notice of the commencement and completion of the work
• Soil to be laid
down in accordance with the Welsh Government's recovery guidelines in
MTAN1: Aggregates.
• After-care provision for a 5 year
period after seeding the site to include provision for the collection of stones, chemical
analysis, land drainage, the timing of the work and any restorative work.
• Comply with
the plans and details of the application,
• It is not permitted to use any
equipment on the site unless adequate dust suppression systems have been
installed for these equipment to prevent the release
of dust.
• Hours of operation are to be 08.00 -
18.00, Monday to Friday, 08.00 - 13.00 on Saturdays and no work on Sundays or
Bank holidays,
• Any work on site must
be suspended and the Planning and Public Protection Service notified
immediately, should any unusual land condition be encountered during the
development,
• Hours of operation of the waste
separation equipment will be 08.00 - 18.00, Monday to Friday, 08.00 - 13.00 on
Saturdays and no work on Sundays or Bank holidays,
• A note to the Applicant to include
the comments of the Water and Environment Unit on the application, advising the
developer to contact them in light of the need for an Ordinary Water Course
Consent for any work that could impact the flow of a water course either
permanently or temporarily,
• A note to the applicant that the
application had been assessed according to the seven
sustainability goals of the Well-being of Future Generations (Wales) Act
(2015).
• Ensure that all the trees enclosed within the Construction Exclusion Zone are protected from building operations throughout the development in accordance with BS5837: 2012 under the surveillance of the project's tree specialist.