DECISION:
To
delegate powers to the Senior Planning Officer to approve the application
subject to completing discussions regarding highways and archaeology matters as
well as material planning conditions relating to:
1.
Time
2.
Compliance with the plans
3.
The development shall be
implemented in accordance with the ecological/tree reports
4.
The operational methods must be followed
as highlighted in the CEMP / pollution prevention plan.
5.
You must act in accordance with the
recommendations of the Flood Risk Assessment
6.
Permitted use of building for any
purposes within Use Class B1 only
7.
Welsh Water conditions
8.
Ensure Welsh / Bilingual signs
9.
NRW Conditions
10.
If, during the development, it is
found that there is contamination that was not previously noted present on the
site, then no further development (unless this is agreed in writing with the
Local Planning Authority) will be undertaken until a remedial strategy
detailing how this unspecified contamination will be addressed is presented to
and approved in writing by the Local Planning Authority.
Notes:
1. Welsh Water
2. Land Drainage
Unit
3. NRW