DECISION:
To approve with conditions
1.
5 years
2.
In accordance with the plans
3.
Highways Conditions
4.
Tree protection fencing must be installed prior to the commencement of
any construction work to avoid damage to the trees and any potential liability
5.
Biodiversity condition – Hedgerow and in line with the green
infrastructure statement
6.
Welsh Water Conditions
7.
Public Protection conditions – noise mitigation measures, installation
of acoustic fencing, details of air source heat pumps, working hours
8.
Submission of a Construction Environmental Management Plan
9.
Land contamination conditions
10.
Archaeological conditions
11.
Welsh Name
12.
Affordable Housing condition
13.
C3 only condition
14.
Removal of permitted rights
Notes
Highways
SuDS
Major
Development