10 Application No C25/0344/11/LL 219 - 231 Stryd Fawr, Bangor, Gwynedd, LL57 1NY
PDF 244 KB
Proposed development for the change of use of
the former Waterloo Inn Public House (A3 use) and part of the former WH Smiths
& USC units (ancillary A1 use) to form 13 no. self-contained residential
flats (C3 use) along with internal alterations and reconfiguration to combine
two existing retail units to provide stalls for retail purposes on the ground
floor.
LOCAL MEMBERS:
Councillor Dylan Fernley and Councillor Nigel Pickavance
Link to relevant background documents
Additional documents:
Decision:
DECISION:
To approve subject to conditions:
1. Time - Five years
2. In accordance with the plans
3. Restrict the use class to C3 residential
dwellings only
4. Restrict the construction hours
5. The
objectives of the Green Infrastructure Statement must be implemented
6. Affordable housing condition
7. Welsh name
Note:
Dŵr Cymru
Minutes:
Proposed
development for the change of use of the former Waterloo Inn Public House (A3
use) and part of the former WH Smiths & USC units (ancillary A1 use) to
form 13 self-contained residential flats (C3 use) along with internal
alterations and reconfiguration to combine two existing retail units to provide
stalls for retail purposes on the ground floor.
a)
The Senior Planning Officer highlighted that it was a full application
for a property located within the boundary of the Sub-Regional Centre and
therefore the principle of developing the site had to be considered against
Policy TAI 1 of the LDP. It was reported that the indicative housing supply
level for Bangor over the LDP period was 969 units. During the period between
2011 and 2025, it was noted that a total of 821 units had been completed in the
city and the windfall land bank i.e. sites with extant planning permission on
sites not designated for housing, stood at 164 units in April 2025. While the
provision was already being addressed through the sites in the land bank, in
such circumstances consideration would be given to the units that had been completed
thus far within the Main Centres tier. Policy PS 17 of the LDP stated that 53%
of housing growth would be located within the Sub-Regional Centre and Urban
Service Centres with a shortfall of 135 units in terms of windfall provision
within this tier.
By adding
13 residential units to the housing stock, this development would help to
contribute towards the LDP's housing targets in a way that responded positively
to the requirements of the local housing market and, therefore, it was believed
that the proposal could be accepted under TAI 1 and PS 17 of the LDP. It was
noted that Policy TAI 9 of the LDP approved the sub-division of existing
properties into self-contained flats provided they conformed to a number of criteria discussed in the report. It was believed
that the proposal was acceptable based on the requirements of Policy TAI 9.
Reference
was made to the Housing Mix assessment, which was part of the Welsh Language
Impact Assessment submitted, which noted that the projections of the Gwynedd
Local Housing Market Assessment 2018-2023 showed a continuous growth in the
number of 1 and 2 people households against a consistent shortage of suitable
property. It was highlighted that the assessment indicated that while there was
good provision for the student accommodation market in Bangor, there was a
significant shortage in the young professionals' market for high-quality units.
It was considered that sufficient evidence had been submitted that there was a
local demand for the size and type of units proposed here and, therefore, that
the housing mix was appropriate and complied with policy TAI 8.
The site was located in a mixed-use area, which included residential uses as well as commercial and business uses. It was not considered that there would be a significant impact on the residential amenities of nearby properties in terms of over-looking ... view the full minutes text for item 10